# 1 MWh (500 kW) battery storage for business in Ukraine: 2026 BESS price

> A 1 MWh / 500 kW battery storage system for a business costs UAH 8,930,000–13,270,000 turnkey in Ukraine (UAH 8,934–13,274 per kWh, excl. VAT, prices of 4 October 2026). At full power it runs for about 1.7 h, at half power about 3.4 h. On day-ahead price shifting SolarPlan's model gives a payback of about 5 years.

_Prices as of 4 October 2026_

- [Plan storage for my business](https://solarplan.app/plan/new?segment=business&region=UA&need=storage)
- [Get offers from installers](https://solarplan.app/plan/new?segment=business&region=UA&intent=request&need=storage)

- **Turnkey price:** UAH 8,930,000–13,270,000 (excluding VAT)
- **Per kWh:** UAH 8,934–13,274 (≈ €175–260 per kWh)
- **Backup:** 1.7 h (at full power, 500 kW)
- **Payback:** 5 years (day-ahead price shifting, central case)

## What it powers and for how long

Hours a full 1 MWh battery runs at a constant load (usable 900 kWh, 90% efficiency):

| Load | Hours |
| --- | --- |
| Full power, 500 kW | 1.7 h |
| Half power, 250 kW | 3.4 h |
| A quarter of the power, 125 kW | 6.8 h |

**Where this size fits:** Factories, agro-processing and water utilities, often with a solar plant on the roof or the ground.

## Price and what it includes

- **Turnkey price:** UAH 8,930,000–13,270,000 (excluding VAT)
- **Per kWh:** UAH 8,934–13,274
- **In euros:** €175,000–260,000 · €175–260/kWh
- **Prices as of:** 4 October 2026
- **Exchange rate:** NBU official rate 51.05 UAH/€ on 3 Nov 2026

Included: LFP battery cabinets or a container, the power conversion system (PCS), energy management (EMS) and monitoring, installation and commissioning.

Priced per site, not included: transformer and switchgear, fire suppression, foundation, design and the grid-connection fee.

## Payback

Charging in the cheap night hours and discharging in the evening peak, the battery earns about UAH 2,090,000 a year in SolarPlan's model (UAH 1,652,000–2,530,000): a payback of about 5 years (4–8 years).

As backup instead of a diesel generator: fuel alone costs about UAH 30 per kWh, a battery cycle about UAH 2.3 per kWh (the price spread over 5,475 cycles). ([Главком, 25 September 2026](https://glavcom.ua/economics/personal-money/benzin-ta-dizel-podorozhali-tsini-na-palne-25-veresnja-2026-1145128.html))

For comparison, the market operator's own model gives about 5 years for a 1 MW / 1 MWh battery. ([Forbes.ua (Оператор ринку), 21 April 2026](https://forbes.ua/news/okupnist-do-4-rokiv-operator-rinku-viznachiv-nayefektivnishu-model-ustanovki-zberigannya-energii-21042026-38146))

**Assumptions:**

- Day-ahead spread 6,000–9,000 UAH/MWh, price cap 15,000 UAH/MWh; the company buys at hourly day-ahead prices. ([LIGA.net (С. Кравчук), 17 July 2026](https://blog.liga.net/user/skravchuk/article/59774))
- One full cycle a day, 90% round-trip efficiency, 15-year life, 1% of the price a year for service; excl. VAT, no grants.

## Rules

- No licence is needed for energy storage up to 5 MW (NEURC resolution No. 789 of 26 May 2026; the threshold used to be 150 kW). ([ЛІГА:ЗАКОН (НКРЕКП № 789), 26 May 2026](https://biz.ligazakon.net/news/244387_nkrekp-sprostila-umovi-dlya-sistem-zbergannya-energ-ltsenzyniy-porg-pdnyato-do-5-mvt))
- Behind the meter, without selling stored energy to the grid, the battery is part of the consumer's installation; connection inside the consumer's network is in practice limited to about 1 MW.
- VAT and import duty on lithium batteries and inverters are 0% until 1 January 2029. ([Forbes.ua, 29 January 2026](https://forbes.ua/news/podatkovi-pilgi-na-vvezennya-energetichnogo-obladnannya-prodovzhili-do-2029-roku-29012026-35902))

## Loans, grants and tax relief

- 5-7-9 business loans: up to UAH 250,000,000 for up to 10 years for solar and storage (the 0% energy loan covers generators only). ([Кабінет Міністрів України, 2026](https://energy.kmu.gov.ua/dostupni-kredyty-5-7-9-dlya-energostijkosti-biznesu/))
- EBRD ESSF loans through partner banks: an EU grant of 10–30% of the investment; loan terms on request at the bank. ([EBRD (ESSF), 2026](https://www.ebrd.com/home/what-we-do/where-we-invest/ukraine/essf-ukraine.html))

## Questions

### How much does a 1 MWh battery cost in Ukraine?

UAH 8,930,000–13,270,000 turnkey excl. VAT (UAH 8,934–13,274 per kWh) as of 4 October 2026: battery cabinets or container, PCS, EMS, installation and commissioning. Transformer, fire suppression, foundation and the connection fee are priced per site.

### How many hours of backup does a 1 MWh battery give?

About 1.7 h at full power (500 kW), 3.4 h at half power and 6.8 h at a quarter of the power.

### MW or MWh: what is the difference?

MW is power (how much the system delivers at a moment), MWh is the energy stored. 1 MWh / 500 kW runs about 1.7 h at full power. The business standard is 2 hours: 1 MW / 2 MWh. Always compare both numbers.

### Does a 1 MWh battery pay back?

Charging in the cheap night hours and discharging in the evening peak, the battery earns about UAH 2,090,000 a year in SolarPlan's model (UAH 1,652,000–2,530,000): a payback of about 5 years (4–8 years). As backup instead of a diesel generator: fuel alone costs about UAH 30 per kWh, a battery cycle about UAH 2.3 per kWh (the price spread over 5,475 cycles).

### Is a licence or permit needed?

No licence is needed for energy storage up to 5 MW (NEURC resolution No. 789 of 26 May 2026; the threshold used to be 150 kW). Behind the meter, without selling stored energy to the grid, the battery is part of the consumer's installation; connection inside the consumer's network is in practice limited to about 1 MW. VAT and import duty on lithium batteries and inverters are 0% until 1 January 2029.

### Which loans, grants or tax relief apply?

5-7-9 business loans: up to UAH 250,000,000 for up to 10 years for solar and storage (the 0% energy loan covers generators only). EBRD ESSF loans through partner banks: an EU grant of 10–30% of the investment; loan terms on request at the bank.

## Other sizes

- [500 kWh / 250 kW](https://solarplan.app/solar/ukraine/storage/business-500-kwh)
- [2 MWh / 1 MW](https://solarplan.app/solar/ukraine/storage/business-2-mwh)
- [250 kWh / 125 kW](https://solarplan.app/solar/ukraine/storage/business-250-kwh)
- [100 kWh / 50 kW](https://solarplan.app/solar/ukraine/storage/business-100-kwh)
- [5 kWh](https://solarplan.app/solar/ukraine/storage/5-kwh)
- [All battery sizes](https://solarplan.app/solar/ukraine/storage)
- [Storage price index](https://solarplan.app/storage-price-index)

## Where these numbers come from

SolarPlan's storage engine, the same one that prices every battery plan: turnkey price bands of 4 October 2026, an hourly model of a typical day and the stated assumptions. Model figures, not a quote.